Jam schedule: Thu Nov 12 00:00 to Sun Nov 15 20:59 ET
All times ET (EST, UTC minus 5; daylight time ended Nov 1). itch shows the deadline as 2026-11-16 01:59 UTC: same moment. Our deadline is Sun 4:00 PM. The 5 hours after are buffer, not work time.
The crew
| Agent | Machine | Owns |
|---|---|---|
| Producer | laptop (hub chat) | The plan, cuts, the lock calls, the dev log editor, messages to Don |
| Editor driver | laptop | The only agent that drives the Unreal editor through MCP. One driver, so prompts never collide. Others hand it tickets. |
| Gameplay coder | laptop (files) | Blueprint logic, built from Python editor scripts in git that the driver runs. Blueprint only, no C++: tower 2 has no compiler and the packaging and hot spare plan depend on a content only project (MCP-RUNBOOK). |
| Level designer | laptop (files, then driver) | Layout, blockout, lighting plan, guidance |
| Art lead | tower 1 | Style frames, textures, image to 3D, decals, UI art (FLUX, FLUX.2 klein, TRELLIS.2, critics) |
| Audio lead | tower 1 | Music (ACE-Step), SFX (see SUBMISSION-KIT on Stable Audio; Kenney CC0 library as sourced filler), voices (Chatterbox, Kokoro), mix |
| Build and QA | tower 2, plus the laptop for video | Packaging, clean machine runs, bot playtests, perf on AMD, hot spare editor. Video capture and encode run on the laptop (record-obs.ps1 needs NVENC; tower 2 is AMD and can't show the game window headless). |
| Review panel | any | Fresh eyed reviewers per STANDARDS.md; they never review their own work |
| Scribe | any | Dev log notes every 2 hours from git, tickets and the asset registry |
Tower 1's GPU is shared: the critic model and ComfyUI can't run at once. The lab GPU lock decides; art and audio queue through it.
Each agent runs at its job's tier (studio ORG.md, "Helpers and effort"; Don, 2026-11-10). Opus for judgment: the producer, the design agent, the review panel, and the leads' look and sound picks. Sonnet (worker) for scoped tickets with a check: Blueprint scripts, blockout scripts, batch specs, dev log drafts. Haiku (scout, log-reader) for searches, overnight log triage, the scribe's gathering, and checking that files exist and measure right. A job moves up one tier only after its check fails twice. Fable 5.2 is for Saturday only (see Sat Nov 14).
Golden rules for the four days
-
Always shippable from Thursday 23:00. Every good package goes to tower 2 and tower 1 as
golden/<time>.zip. If everything burns down, we submit the last golden. -
Push every hour. The driver runs
prep/scripts/push.ps1on the hour: it pushes toorigin, tower 1's bare mirror. At each golden, tower 2 pulls the project from tower 1 so it can open it as the hot spare. Both are in the house; the off site copy is the golden on Don's Draft itch page from Saturday (RISKS 15). - Locks are locks. Feature lock Fri 22:00. Content lock Sat 20:00. Code freeze Sun 10:00 (crash fixes only).
- Night is for machines. Midnight to 8 AM runs generation, bakes, packaging and bot playtests. Claude heavy work runs in the day so we don't burn the token budget while nobody can act on the results. The one exception is Thursday's first night: the kickoff runs agents from midnight to write the design and build the skeleton.
-
Builds for Don are unzipped on the laptop to
D:\megajam\builds\<time>\with a desktop shortcut, after the review panel has played them.
Milestones
| # | When | Milestone |
|---|---|---|
| M0 | Thu 00:00 | Kickoff: theme-day/DESIGN.md written from Don's pick (done by 01:30); blank Blueprint project created |
| M1 | Thu 02:00 | Empty project packages and runs on tower 2 with our settings (proof of the pipeline) |
| M2 | Thu 09:00 | 3 real-look style frames (FLUX.2 klein from the style lock, canon checked); studio picks one. Internal; Don may glance. |
| M3 | Thu 14:00 | Core verb works in greybox on pad, keys and touch (internal only) |
| M4 | Thu 22:00 | Playable greybox loop start to finish (internal); packaged by 23:00; first golden |
| M5 | Fri 12:00 | First packaged build with the real look in the first zone |
| M6 | Fri 18:00 | Don playtest 1 (three inputs, 30 min) |
| M7 | Fri 22:00 | Feature lock |
| M8 | Sat 14:00 | Don playtest 2 (full game, real art everywhere) |
| M9 | Sat 20:00 | Content lock (all art, audio, voice in) |
| M10 | Sun 10:00 | Release candidate packaged; code freeze |
| M11 | Sun 13:00 | Video, dev log and submission kit final |
| M12 | Sun 14:00 to 16:00 | Don uploads and submits |
"Greybox" at M3 and M4 is internal. Don never gets a link to it (show the look first). His first build at M6 has real art in at least the first zone, and anything still gray is named in the message.
Wed Nov 11 (theme day)
Morning: the engine gate (MCP-RUNBOOK.md, "Engine choice"). 5.9.0 if it passes every check, else 5.8.4; Don leans to 5.9. Record the result in MCP-RUNBOOK.md before 2 PM, so the theme day prompts name the right engine. Then see PLAYBOOK.md. Don's only job: pick at 4:20 PM (or say "your call"). Wednesday ends at the pick: the design, level layout and prompt sheets are written from 00:00 Thursday, so nothing that looks like game content predates the window (rule 7h). At 6 PM the producer arms the midnight kickoff as a one time check in, so nobody has to be awake.
Thu Nov 12: build the core
| Time | Laptop (Unreal, MCP) | Tower 1 (AI gen) | Tower 2 (build, test) | Don |
|---|---|---|---|---|
| 00:00 | Producer and design agent write theme-day/DESIGN.md from the pick (by 01:30; fresh reviewer by 02:00). Driver creates the blank Blueprint project in game/, project settings from MCP-RUNBOOK, Enhanced Input with pad, keys and touch maps | 01:30: style frame prompts from DESIGN.md go in the queue | Pull project skeleton | asleep |
| 01:00 | Player pawn and camera, first pass | Look dev batch 1 (environment and key props, 3 directions) | Package the empty project (Development, app local prerequisites) | asleep |
| 02:00 | Core verb prototype begins | Batch 1 critics (qwen3-vl, HPS) | M1: package it; the laptop smoke tests the zip; time it | asleep |
| 03:00 to 07:00 | Core verb prototype; greybox of the level from the layout sketch | Music sketches (2 directions), SFX first list (one per action) | Bot playtest harness pointed at the project (input replay) | asleep |
| 08:00 | Driver check in; producer reviews overnight output | Style frames: FLUX.2 klein from the style lock, canon first, critics; no greybox in any frame | Overnight results report | asleep |
| 09:00 | M2: studio picks the look | Lock the style bible; hero asset list goes into the queue | optional 5 min: glance at the chosen frame | |
| 10:00 | Core verb tuning (feel targets) | Hero asset 1 to 3: image, then TRELLIS.2, then cleanup | ||
| 11:00 | Core verb tuning; touch on screen controls | Hero assets continue | Package attempt 2 | |
| 12:00 | Level blockout zone 1 | Materials pass 1 (AI PBR plus CC0 filler) | Perf check on AMD | |
| 13:00 | Level blockout zone 2 | Music theme draft (ACE-Step, 3 takes) | ||
| 14:00 | M3: core verb on all three inputs; review panel plays it | SFX batch 1 (8 takes each, auto pick; tool per SUBMISSION-KIT's Stable Audio note) | Input test: pad, keys, touch | |
| 15:00 | Fix review findings | Hero assets 4 to 6 | ||
| 16:00 | Level blockout zone 3; goal and fail states | Hero assets continue | ||
| 17:00 | Win and lose flow, restart in one second | Music: pick the theme, make the second intensity | ||
| 18:00 | Main menu, pause, settings (volume per channel, reduce motion, reduce flashing) | UI art (no model lettering; real fonts) | ||
| 19:00 | Loop end to end in greybox | SFX batch 2 | ||
| 20:00 | Fix | Voice bible and line list (if the design has voice) | ||
| 21:00 | Fix | Package attempt 3 | ||
| 22:00 | M4: full loop playable. Review panel plays | Bot playtest: can it finish? time to finish | ||
| 23:00 | Commit, push | Overnight queue: rest of hero assets, environment set, music stems | First golden build |
Fri Nov 13: the look goes in, features lock
| Time | Laptop | Tower 1 | Tower 2 | Don |
|---|---|---|---|---|
| 00:00 to 07:00 | Idle or light jobs (lighting builds if any) | Overnight art and audio queue | Bot playtests on golden (stuck points, crash hunt); package nightly | asleep |
| 08:00 | Triage overnight results | Critics on overnight assets; reject and requeue | Report | |
| 09:00 | Import hero assets into zone 1; lighting pass zone 1 | Requeue rejects | ||
| 10:00 | Zone 1 dressing; Niagara pass zone 1 | Environment set continues | ||
| 11:00 | Music and SFX hooked to events zone 1 | Voices (if any): record, pick by Whisper and ear | Package | |
| 12:00 | M5: real look in zone 1 packaged | Smoke test (zip to the laptop), perf AMD | ||
| 13:00 | Zone 2 assets and lighting | Zone 3 assets | ||
| 14:00 | Zone 2 dressing; signature moment build | |||
| 15:00 | Signature moment build | |||
| 16:00 | Review panel full pass (all STANDARDS sections) | Flash check, colorblind sheet on captures | ||
| 17:00 | Fix the worst findings; package for Don | Package, golden 2; unzip to the laptop's builds folder for Don | ||
| 18:00 | M6: Playtest 1, 30 min. Pad first, then keys and mouse, then touch screen. What to try comes in one message. | |||
| 19:00 | Fold in Don's notes (each one becomes a STANDARDS rule if new) | send notes by text or voice; create the itch game page as a Draft | ||
| 20:00 | Fix | |||
| 21:00 | Fix; producer runs the cut list against what's left | |||
| 22:00 | M7: feature lock. No new mechanics after this. | Overnight queue: zone 3 dressing assets, music final stems, SFX batch 3 | Package, golden 3 | |
| 23:00 | Commit, push | Overnight bot playtests |
Sat Nov 14: content and audio
Fable 5.2 runs Saturday's integration and polish push, on Don's plan resets (Don, 2026-11-10). The second reset is Sunday insurance. Thursday's kickoff night and Friday run on normal limits.
| Time | Laptop | Tower 1 | Tower 2 | Don |
|---|---|---|---|---|
| 00:00 to 07:00 | Light bakes if used | Overnight queue | Bots, nightly package | asleep |
| 08:00 | Triage | Critics, requeue | Report | |
| 09:00 | Zone 3 dressing and lighting | Last asset rejects | ||
| 10:00 | Full audio pass: every action has a sound, music states, ambience per zone | Mix stems | ||
| 11:00 | Subtitles with speaker names (if voice); credits screen from the asset registry | |||
| 12:00 | Review panel full pass | Flash and colorblind checks | ||
| 13:00 | Fix; package for Don | Package, golden 4 | ||
| 14:00 | M8: Playtest 2, 30 min. The whole game on all three inputs. Then upload golden 4 to the Draft itch page as a placeholder. | |||
| 15:00 | Fold in Don's notes | notes | ||
| 16:00 | Polish: camera, feel, transitions (designed, never a bare fade) | |||
| 17:00 | Polish; title screen and end screen. Video: first capture pass on the laptop from golden 4 (record-obs.ps1, 1080p60; the bot harness replays a scripted best run) | |||
| 18:00 | Polish | Loudness pass (peaks at minus 1 dBFS or lower) | ||
| 19:00 | Last content in | |||
| 20:00 | M9: content lock. | Package, golden 5 | ||
| 21:00 | Bug list only; video rough cut on the laptop (ffmpeg, VIDEO.md) | |||
| 22:00 | Bug list only | |||
| 23:00 | Commit, push | Overnight: soak test (play for 2 hours), bots |
Sun Nov 15: ship
| Time | Laptop | Tower 1 | Tower 2 | Don |
|---|---|---|---|---|
| 00:00 to 07:00 | idle | idle (or video stills) | Soak test, bots, nightly package | asleep |
| 08:00 | Crash and blocker fixes from the night | Report | ||
| 09:00 | Fixes | |||
| 10:00 | M10: release candidate. Code freeze. | Package RC; smoke test from a fresh folder; zip TeamName_GameName.zip; size check under 1 GB | ||
| 10:30 | Review panel plays the RC (STANDARDS full pass); fixes only for blockers | RC run on all three inputs; perf AMD | ||
| 11:30 | Spare editor on standby | RC check, 20 min. Play the RC from the laptop's builds folder. Say ship or name a blocker. | ||
| 12:00 | Blocker fix only if Don named one (then repackage by 12:45). Video final capture and cut on the laptop from the RC | |||
| 12:30 | Fresh reviewer runs the kit's pre upload checklist on the RC, video file and dev log text | |||
| 13:00 | M11: video, dev log and kit final | |||
| 13:30 | Read the dev log (15 min) and approve | |||
| 14:00 | Upload the video to YouTube as unlisted. Publish the dev log on the itch page. Replace the placeholder zip with the RC zip. | |||
| 15:00 | Kit's post upload checklist from a logged out browser: page opens, zip downloads and its hash matches the RC, video plays, dev log opens. Then Don submits. | Click Submit on the jam page, fields pasted from SUBMISSION-KIT | ||
| 15:30 | Screenshot the "submitted" page | |||
| 16:00 | Done. | |||
| 16:00 to 20:59 | Buffer. If anything failed above, fix and edit the same entry (one submission only, rule 2; itch allows edits until the deadline) |
Hard stop: if we are not submitted by 6:00 PM, Don submits the last golden as is.
When Don is needed (all of it)
| When | What | Time |
|---|---|---|
| Done 2026-11-09 | Joined the jam; name and Epic email recorded. | |
| Before Wed 2 PM | In prep\toolcheck, run claude once: log in, trust the folder, approve unreal-mcp (MCP-RUNBOOK). | 5 min |
| Before Wed 2 PM | Upload rehearsal: upload the ToolCheck zip (about 355 MB) to a throwaway Draft itch page and note the time (RISKS 2 and 14). | 15 min |
| Done 2026-11-10 | Paused for the jam: tower 1's byok-watch.timer, the laptop's three "Studio nightly jobs" tasks and "Studio dashboard refresh". The backup, queue agents and tower 2 CI keep running. Re-enable all of it on Nov 16. | |
| Before Wed 2 PM (optional) | Pause Windows Update on the laptop and tower 2 until Nov 16, so nothing reboots mid jam (a system setting, so only Don). | 5 min |
| Wed 4:20 PM | Pick one of three pitches, or "your call". | 5 to 25 min |
| Thu 9 AM (optional) | Glance at the chosen look. | 5 min |
| Fri 6 PM | Playtest 1: pad, keys and mouse, touch. Then create the itch game page as a Draft (title, no files yet). | 40 min |
| Sat 2 PM | Playtest 2: the full game. Then upload golden 4 to the Draft page as a placeholder, so Sunday is a swap. | 45 min |
| Sun 11:30 AM | RC check: ship or name a blocker. | 20 min |
| Sun 1:30 PM | Read and approve the dev log. | 15 min |
| Sun 2 PM to 3:30 PM | Upload video (unlisted), publish dev log, upload zip, click Submit. | 60 to 90 min |
About 5 hours of Don across 5 days. He sleeps normal nights; nothing needs him between 11 PM and 8 AM.